Abuja Reports

FG Set to Complete Abuja-Kaduna Road in 2024 

Published

on

The Federal Government has set plans in motion to complete and deliver the remaining section of Abuja-Kaduna road before the end of 2024.

Recall that successive governments had in the past made similar promises for the construction of the said road since the  award of contract on December 20, 2018.

The Minister of Works, Senator Dave Umahi, made the latest promise at a meeting with directors of his ministry in Abuja yesterday.

Umahi said the ministry under his watch, was prepared to remove all contractual bottlenecks and ensure delivery of the project for the benefit of Nigerians before the end of 2024.

“We have about 1.7 kilometers left of Abuja-Kaduna in two sections. The ministry has some supervision work to be done tomorrow on that road and we will be advised on the real designs of the two sections.

“Funding is also an issue because it is under the presidential development fund initiative gotten from looted funds. I have had to discuss with Mr president about the importance of the road for all Northerners.

“But I won’t be able to go back to him until we re-scope it because the project was N165bn before and a review brought the cost to N655bn but today the contractor is asking for N1.35trillion and the government cannot afford it.

“What they are asking is very wrong. So, we are looking at existing sub-grade and see what we can do about it.

”We are also looking at the first 40km to be constructed by Dangote under the tax credit scheme,’’ Umahi said.

 

Leave a Reply

Your email address will not be published. Required fields are marked *

Trending